2018
August
THE SANJEO WORK BEGINS AND THE LAYING OF THE DRINKING WATER NETWORK

From the development firm of Urbanization Costa Dorada  families who have acquired  In the first days of June, the necessary works began to be carried out to advance rapidly in the laying of the drinking water network, sanjeo works were carried out, so some streets must be traveled with caution.

The works  They are carried out according to the masterplan and include the construction of its own cistern, anticipating the future development of the area and alleviating the overload of the aqueduct that passes a few meters from the lot.

As previously reported, Urbanización Costa Dorada, together with the contracting companies, are committed to completing the work as soon as possible.  accompanying buyers who are already doing preliminary work on their land.

costa dorada_agosto.png
2018
August
TRANSFORMERS AND MATERIALS MOVED TO COMPLETE THE 2nd STAGE

The medium voltage transformers, already with the technical approval of EDERSA, were transported to Playas Doradas, and will be installed in the next few days.

As part of the work to provide the Urbanization with electricity, cuts of electricity service to Playas Doradas are also being planned for the month of November.  in order to carry out the movement of the existing medium voltage line from the old line to one of the streets that crosses the lot and each of its stages from north to south. In addition, the complementary works are progressing in parallel at a good pace to reach the summer 2019 with big changes.

The person in charge of managing the development infrastructure works mentioned that "the materials have already been purchased in their entirety, this is one of the latest shipments and we aim that all the people who visit us this next season can appreciate the advances made in infrastructure. ”.

costa dorada_mayo obras.png
2018
May
THE LAYING OF THE ELECTRICAL WIRING MARKS THE ADVANCES IN INFRASTRUCTURE

After the recess marked by the successful summer 2018, the laying of cables continues to be carried out on the 21 blocks of the first and second stages, more than 10,500 meters of cables will be placed and in addition, the placement of 150 w high-pressure sodium luminaires will be completed. On the other hand, a contract has been signed with the firm that will carry out the work to provide drinking water to the urbanization and in the coming weeks the materials will be purchased, planning the start of the work for the month of September.

Servicios Playas Doradas
2017.
October
ELECTRICAL WORK IN THE URBANIZATION ADVANCES AT A GOOD PACE

The person in charge of the work commented that "it is a project that is being carried out purely and exclusively with local labor. Today we are in full execution and advancing according to the agreed deadlines."

The company that carries out the work is originally from Sierra Grande, as well as its staff. Its owner expressed "We want to thank those responsible for the subdivision because from the first moment they made surveys to occupy a majority of the local workforce", and added: "It was like this that not long ago, we had confirmation, we signed a contract and quickly We comply with all the legal and safety requirements to carry out the work in the best conditions ”, concluded the businessman.

At this moment, work is being done on 21 blocks, placing more than 250 poles for the laying of cables and placement of luminaires, on the other hand, the concrete columns have arrived on the plot and the transformers are already in the supervision stage at the supplier company. of energy.

2017.
August
Obra Electrica Loteo
ALL READY TO START THE ELECTRIFICATION WORK OF THE LOT

This is the work projected as part of the masterplan to provide the Urbanization with electrical energy, and includes the shifting of the existing medium voltage line from the old layout to one of the main streets of the development, in addition to complementary works such as the placement of more than 240 150W high pressure sodium vapor luminaires

All the purchased items were transported to Playas Doradas, awaiting the start of the work in the next few days.

The assumed commitment establishes that Urbanización Costa Dorada , through its Administrator Trustee, will supply the blocks that make up the lot with power lines and public lighting, in addition to the water network, which is projected to start in the coming months.

In his speech, the person in charge of managing the development infrastructure works mentioned that "today is an important day for the Urbanization since once this work is completed, the First and Second Stages will have the electricity supply in all their blocks".

Costa Dorada
2016
October
STREETS, AVENUES AND BOULEVARES WERE CONSOLIDATED FOR THE SEASON

The contracted machine team  is finishing the leveling and consolidation works of the streets and boulevards of the first and  second stage of the project, with the aim of complying with the work plan outlined for this year 2016. 
The tasks are part of the masterplan that proposes the subdivision of the 93-hectare property in five stages, with more than a thousand lots to offer for sale.
The proximity of summer and with it the influx of visitors in greater numbers demanded a set of works that have the purpose of adapting the streets and accesses of the new urbanization. Each of these works involves works of different magnitude according to its specific characteristics.
The works are being carried out in the six streets that run through the urbanization from north to south, on the coastal road of undeniable attractiveness and  on the boulevards of forty meters in the direction of the sea of the first two stages.
These works, which were projected by professionals of the company, are part of the development program and  marketing that it proposes to have for the purchase and  immediate possession 250 lots of the first stage during the summer 2016/2017. 
The works include the qualification and signaling of the access to the new coastal road,  the aforementioned opening and leveling of the streets that make up the masterplan grid, and an improvement of the road that allows reaching the beach known as "Las Casitas".
In this way, Urbanización Costa Dorada foresees for this year an important improvement in the road infrastructure in the Punta Colorada area, offering an alternative to the already  existing with new routes, which are especially important as a basis for the development of this new offer among the coastal attractions of the area.